Michele Corda the Equipment Supervisor for Costa Fortuna and Jim Casavant of APE were on hand for the 1st Caisson driven with their new APE D50 outfitted with Costa Fortuna’s very well thought out Offshore Driving System. The System uses a Large drive plate with a Heavy Duty Pipe stub welded in the center, the Hammer in a Short Lead section is then lower onto the stub and Driving is complete.
The D50 will be used to drive the 2.5 mt. dia. x 58 mt. long Caisson’s for the new 3,000 meter Ponte Luis Inacio Lula da Silva Bridge. The Overall Shaft depth is 85 mt.

APE looks forward to many more projects with Costa Fortuna in the future.